TENTATIVE PAINTING SCHEDULE

Address P/W Prime & Paint Doors & Lanis Notes
20141,20137,20133,20129,20121 & 20117 Done 3/6 - 3/10 Tuesday 3/14 These are notes
20111,20109,20105,20101,20097,20093,20089 & 20085 Done 3/13- 3/17 Tuesday 3/21
20081,20071,20073,20069,20065,20061,20057 & 20053 3/20/17 3/20 - 3/24 Tuesday 3/28
20049,20045,20037,20033,20029,20025,20021 & 20017 3/20/17 3/27 - 3/31 Tuesday 4/4
20013,20011,20009,20005,20004,20008,20012 & 20016 3/31/17 4/3 - 4/7 Tuesday 4/11
20020,20025,20028,20032,20036,20040,20044 & 20048 4/4/17 4/10 - 4/14 Tuesday 4/18
20052,20056,20060,20064,20068,20072,20076 & 20080 4/14/17 4/17 - 4/21 Tuesday 4/25
20084,20088,20092,20096,20100,20104,20108 & 20112 4/21/17 4/24 - 4/28 Tuesday 5/2
20116,20120,20124,20128,20132,20136 & 20140 4/28/17 5/1 - 5/5 Tuesday 5/9

Please be advised...these schedules are tentative